< Close
CURRENT INFORMATION ABOUT POWER OUTAGES

Thursday, April 15, 2021

Scheduled Outage Notice for: Dededo/Route 3 Area, 22 April 2021

For Release: On Receipt
End Date: Thursday, 22 April 2021 @ 2:30 PM
 
The Guam Power Authority advises that there will be a scheduled power outage and road closure as follows: 
 
Thursday, 22 April 2021
From 8:30 AM to 2:30 PM (6 hours)
 
The area(s) affected include:  Route 3 Dededo, Chalan Inda and customers in the surrounding area.
 
REASON: GPA Line crews will be replacing and installing concrete poles; and removing and installing new overhead power line wires to improve power quality and reliability of the islandwide power system.
 
Customers using backup generators, please ensure your main breaker is in the OPEN position to ensure the safety of the GPA crews working on the lines.
 
GPA regrets the inconvenience caused to customers in these areas, but the outage is necessary as a safety precaution while the GPA crews are performing this work.
 
Your cooperation is appreciated.
 
# # #
 
Editor’s note: customers may view this power outage information on GPA’s Facebook page and GPA Instagram